HANGA AQUEDUCT
The Company has executed the work of construction of Hanga Aqueduct for Maharashtra Irrigation Department in a contract period of 3 years. This is 1.5 Km. Long PSC Aqueduct of 28 spans of 45 mts.,each. The work involved 1.00 lakh cum of earthwork for embankment, 20,000 cum of Masonry, 39,528 cum of Concrete, 14,560 Cum of PS Concrete, 2,080 MT of Reinforcement and 521 MT of HT Steel. The work started in Sep.,1996 and completed in Sep.,1998 .i.e 12 months ahead of schedule period. For its outstanding performance in the execution of work and early completion of work, Prasad & Co was awarded a GOLD MEDAL & CERTIFICATE OF MERIT by the Government of Maharashtra in addition to incentive as per agreement.